Guide · Building

A construction budget you can actually change

Start from the floor area times a cost per square metre and add a contingency for a quick estimate. Then add a section per job, with quantities and unit prices for bricks, cement, sand and labour. Every line keeps its unit, and when a quote changes, the totals below it follow.

By Sigit Kuncoro, who makes Sumi · Updated

The prices here are examples in rupiah, the way an Indonesian RAB (rencana anggaran biaya) is usually written. Use the quotes from your own contractor and suppliers.

A quick estimate from the floor area

Rumah

  1. # rumah type 36
  2. luas = 6 m × 6 m 36 m²
  3. harga = Rp 4,5jt per sq m Rp 4.500.000/m²
  4. bangunan = luas × harga Rp 162.000.000
  5. cadangan = bangunan × 10% Rp 16.200.000
  6. total = bangunan + cadangan Rp 178.200.000

A 36 m² house at an example Rp 4,5 juta per square metre, with 10 % set aside for surprises, comes to Rp 178.200.000. per sq m makes the price an amount per area, so area times price is money.

Detail one job at a time

Dinding

  1. # dinding
  2. dinding = 2.8 m × 24 m 67,20 m²
  3. bata = dinding / 1 sq m × 70 4.704
  4. harga bata = bata × Rp 900 Rp 4.233.600
  5. semen = 12 × Rp 75rb Rp 900.000
  6. pasir = 2 × Rp 1,2jt Rp 2.400.000
  7. tukang = 2 × 30 × Rp 175rb Rp 10.500.000
  8. total = harga bata + semen + pasir + tukang Rp 18.033.600

Keep the whole RAB in one sheet

  1. One # section per job: foundation, walls, roof, electrical, finishing, each ending in its own total line. Fold the ones you are not working on.
  2. Name the totals of each section and add them on a last line for the whole build.
  3. Keep a contingency line, like cadangan = bangunan × 10%, so changes don’t come out of nowhere.
  4. Amounts in rupiah read naturally: Rp 4,5jt, 75rb, 1,2 miliar; see rupiah amounts.

Ringkasan

Hitung RAB rumah di Sumi baris demi baris: luas bangunan dikali harga per meter persegi, tambah dana cadangan, lalu rincian tiap pekerjaan (bata, semen, pasir, upah tukang). Harga di halaman ini hanya contoh; pakai penawaran dari kontraktor Anda. Ubah satu harga, semua total ikut berubah.

Questions

How do I estimate the cost of building a house?

Multiply the floor area by a cost per square metre from your contractor or a recent local quote, then add a contingency, often around 10 %. In Sumi: luas = 6 m × 6 m, harga = Rp 4,5jt per sq m, bangunan = luas × harga, total = bangunan + 10%.

Can I write a detailed RAB (rencana anggaran biaya) in Sumi?

Yes. Write one section per job with a # line, and inside it the quantities and prices: bricks per square metre, sacks of cement, days of labour times the daily wage. End each section with its own total line, and fold the ones you are not working on.

Bagaimana cara menghitung biaya bangun rumah per meter?

Kalikan luas bangunan dengan harga per meter persegi dari kontraktor, lalu tambahkan dana cadangan, misalnya 10 %. Di Sumi: luas = 6 m × 6 m, harga = Rp 4,5jt per sq m, bangunan = luas × harga.